Update on the shade structure build, April 6, 2022. Jai Pal says: “The Shade Structure curved roof beams will be ready to ship from Portland this Friday, April 8th. Once the GluLam beams arrive, we will prepare and seal the wood, install them with the steel columns, and into the existing beam saddles. A concrete grade beam will be installed surrounding the steel columns below the ground, which will stabilize the whole structure. Upon completion of the roof frame and when funds are available, we will install the roof framing and a waterproof roof membrane to cover it. Right now we are projecting four weeks to build the frame and roof structure.”